Our worship & service continue during the transformation of our building

Click here for more information

Update: July Site Visit

Update 15th July 2025

Here’s a selection of photos from the latest site visit to the work to create The Link Centre & Gateway Lodge.

~ Trinity Hall plaster/ceiling repairs and redecoration are finished. The wainscotting is complete and painted, the new radiators and new uplighters are installed. It is bright and light.

~ The balcony panelling is painted; the filigree work is regilded, and new feature lights are installed.

~ The new Heritage White paint brings out the colours in the stained-glass.

~ The organ is temporarily screened off – there will be a new wooden screen – to match the balcony panelling

~ Cornerstone’s temporary kitchen in Trinity Hall is built - this kitchen will be removed when the coffee shop returns to the Cornerstone building

~ The Link structural floor slab is complete, as is the large retaining wall, and bricklaying for the Link wall has started

~ Scaffolding is up on the Station Road side (now the Link floor is complete). Repairing/painting windows, repointing, gutter replacement etc is being done - as already completed on the other three sides

~ In Gateway Lodge water pipes for heating, hot and cold water (for the en-suites etc) are installed. There will be a new ceiling below them.

~ The new doors into Trinity Hall from the Church Street Foyer

~ The new access ramp to Trinity Hall is being installed.

 

All of the work is part of Ashbourne Reborn - you can find out more about the programme at www.ashbournereborn.co.uk 

Trinity Hall plaster/ceiling repairs and redecoration are finished. The wainscotting is complete and painted, the new radiators and new uplighters are installed. It is bright and light.The balcony panelling is painted; the filigree work is regilded, and new feature lights are installed. The new Heritage White paint brings out the colours in the stained-glass. The organ is temporarily screened off – there will be a new wooden screen – to match the balcony panelling Cornerstone’s temporary kitchen in Trinity Hall is built - this kitchen will be removed when the coffee shop returns to the Cornerstone building The Link structural floor slab is complete, as is the large retaining wall, and bricklaying for the Link wall has started Scaffolding is up on the Station Road side (now the Link floor is complete). Repairing/painting windows, repointing, gutter replacement etc is being done - as already completed on the other three sides In Gateway Lodge water pipes for heating, hot and cold water (for the en-suites etc) are installed. There will be a new ceiling below them. The new doors into Trinity Hall from the Church Street Foyer The new access ramp to Trinity Hall is being installed.

 

 

 

 

 

Powered by Church Edit