Update: April Site Visit

Update 18th April 2025

Work is progressing well with the transformation of our building into a new hub for the community.

Photos show:

- The inside of Trinity Hall at The Link Centre is currently completely filled with scaffolding. It looks a bit like a giant climbing frame!

- In Trinity Hall, the wooden wainscoting in the main worship & performance space at The Link Centre has been removed for refurbishment.

- In Gateway Lodge, mesh is being applied to the ceiling prior to replastering.

- Work has finished on driving in the piles for the foundations of The Link Centre's new foyer. The piles are now being capped preparatory to the foundation slab being laid.

All of the work is part of Ashbourne Reborn - you can find out more bout the programme at www.ashbournereborn.co.uk 

Photo of the inside of Trinity Hall at The Link Centre with scaffolding completely filling the space. Photo showing that the wainscoting in the main worship & performance space at The Link Centre has been removed for refurbishingPhoto of the inside of Gateway Lodge. Workers are on a telescopic platform working to apply mesh to the ceiling prior to replastering.Work has finished on driving in the piles for the foundations of The Link Centre's new foyer. The piles are now being capped preparatory to the foundation slab being laid.

 

 

 

 